Name: | PEREZ CONSTRUCTION LLC |
Jurisdiction: | Rhode Island |
Entity type: | Domestic Limited Liability Company |
Status: | Activ |
Date of Organization in Rhode Island: | 07 Jan 2015 (10 years ago) |
Identification Number: | 001033238 |
ZIP code: | 02909 |
County: | Providence County |
Principal Address: | 17 CROWNINSHIELD STREET, PROVIDENCE, RI, 02909, USA |
Purpose: | CONSTRUCTION |
Name | Role | Address |
---|---|---|
GUSTAVO PEREZ | Agent | 17 CROWNINSHIELD STREET, PROVIDENCE, RI, 02909, USA |
Number | Name | File Date |
---|---|---|
202444395780 | Annual Report | 2024-01-22 |
202444395960 | Annual Report | 2024-01-22 |
202444394990 | Reinstatement | 2024-01-22 |
202340892680 | Revocation Certificate For Failure to File the Annual Report for the Year | 2023-09-11 |
202337023620 | Revocation Notice For Failure to File An Annual Report | 2023-06-16 |
202221524730 | Annual Report | 2022-07-21 |
202218887840 | Revocation Notice For Failure to File An Annual Report | 2022-06-22 |
202102680720 | Annual Report | 2021-10-05 |
202080222550 | Annual Report | 2020-12-16 |
202080221580 | Annual Report | 2020-12-16 |
Inspection Nr | Report ID | Date Opened | Site Address | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
339845398 | 0112300 | 2014-05-29 | 95 SPRING STREET, WOONSOCKET, RI, 02895 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Type | Complaint |
Activity Nr | 891601 |
Safety | Yes |
Health | Yes |
Violation Items
Citation ID | 01001A |
Citaton Type | Serious |
Standard Cited | 19261101 E06 |
Issuance Date | 2014-11-25 |
Abatement Due Date | 2015-01-13 |
Current Penalty | 1600.0 |
Initial Penalty | 1600.0 |
Final Order | 2014-12-03 |
Nr Instances | 1 |
Nr Exposed | 7 |
Related Event Code (REC) | Complaint |
Gravity | 5 |
FTA Current Penalty | 0.0 |
Citation text line | 29 CFR 1926.1101(e)(6): The employer did not ensure that all asbestos work performed within regulated areas was supervised by a competent person: a) Jobsite Roof: On or about 05/29/2014 employees were removing asbestos shingles and the employer had not provided a competent person to supervise the work performed. |
Citation ID | 01001B |
Citaton Type | Serious |
Standard Cited | 19261101 G08 II B |
Issuance Date | 2014-11-25 |
Current Penalty | 0.0 |
Initial Penalty | 1200.0 |
Final Order | 2014-12-03 |
Nr Instances | 1 |
Nr Exposed | 4 |
Related Event Code (REC) | Complaint |
Gravity | 1 |
FTA Current Penalty | 0.0 |
Citation text line | 29 CFR 1926.1101(g)(8)(ii)(B): Feasible wet methods were not used to remove roofing materials that were not intact or that were rendered not intact during removal: a) Jobsite Roof: On or about 05/29/2014 employees were removing asbestos shingles using a dry method with shovels and roof rippers causing the roofing materials to no longer be intact during removal. |
Citation ID | 01001C |
Citaton Type | Serious |
Standard Cited | 19261101 G08 II E |
Issuance Date | 2014-11-25 |
Current Penalty | 0.0 |
Initial Penalty | 1600.0 |
Final Order | 2014-12-03 |
Nr Instances | 1 |
Nr Exposed | 3 |
Related Event Code (REC) | Complaint |
Gravity | 5 |
FTA Current Penalty | 0.0 |
Citation text line | 29 CFR 1926.1101(g)(8)(ii)(E): Asbestos-containing material was not either carried or passed to the ground by hand or lowered to the ground via covered, dust-tight cute, crane or hoist: a) Jobsite Roof to Ground Dumping and Cleanup Areas: On or about 05/29/2014 employees were removing asbestos shingles on the roof and throwing them off of the roof down onto the ground approximately 25 feet without the use of a chute, crane or hoist. |
Citation ID | 01001D |
Citaton Type | Serious |
Standard Cited | 19261101 G08 II F |
Issuance Date | 2014-11-25 |
Current Penalty | 0.0 |
Initial Penalty | 0.0 |
Final Order | 2014-12-03 |
Nr Instances | 1 |
Nr Exposed | 3 |
Related Event Code (REC) | Complaint |
Gravity | 5 |
FTA Current Penalty | 0.0 |
Citation text line | 29 CFR 1926.1101(g)(8)(ii)(F): Upon being lowered, unwrapped material was not transferred to a closed receptacle in such a manner so as to preclude the dispersion of dust: a) Jobsite Ground Dumping and Cleanup Areas: On or about 05/29/2014 employees were transferring asbestos shingles from the ground to the dumpster and were not provided with a tarp or equivalent to preclude the dispersion of dust. |
Inspection Type | Unprog Other |
Scope | Partial |
Safety/Health | Safety |
Close Conference | 2014-03-19 |
Emphasis | L: FALL |
Case Closed | 2014-09-25 |
Violation Items
Citation ID | 01001A |
Citaton Type | Serious |
Standard Cited | 19260501 B13 |
Issuance Date | 2014-03-25 |
Abatement Due Date | 2014-05-07 |
Current Penalty | 1400.0 |
Initial Penalty | 2800.0 |
Final Order | 2014-04-16 |
Nr Instances | 1 |
Nr Exposed | 3 |
Related Event Code (REC) | Complaint |
Gravity | 10 |
FTA Current Penalty | 0.0 |
Citation text line | 29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b). a. Jobsite; The employer failed to ensure that employees had and adequate means of fall protection when working above 6 feet. |
Citation ID | 01002 |
Citaton Type | Other |
Standard Cited | 19261053 B01 |
Issuance Date | 2014-03-25 |
Abatement Due Date | 2014-04-09 |
Current Penalty | 0.0 |
Initial Penalty | 2800.0 |
Final Order | 2014-04-16 |
Nr Instances | 1 |
Nr Exposed | 3 |
Related Event Code (REC) | Complaint |
FTA Current Penalty | 0.0 |
Citation text line | 29 CFR 1926.1053(b)(1): Portable ladders were used for access to an upper landing surface and the ladder side rails did not extend at least 3 feet (.9 m) above the upper landing surface to which the ladder was used to gain access. a. Jobsite; The employer did not ensure that portable ladder rails extended 3 feet above the upper landing surface. |
Loan Number | Loan Funded Date | SBA Origination Office Code | Loan Delivery Method | Borrower Street Address | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
9103287306 | 2020-05-01 | 0165 | PPP | 17 Crowninshield st, providence, RI, 02909 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
6788198308 | 2021-01-27 | 0165 | PPS | 17 Crowninshield St, Providence, RI, 02909-5207 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Date of last update: 20 Oct 2024
Sources: Rhode Island Department of State