Inspection Type |
Complaint
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2022-10-03
|
Emphasis |
L: FALL
|
Related Activity
Type |
Complaint |
Activity Nr |
1953060 |
Safety |
Yes |
|
Type |
Inspection |
Activity Nr |
1625655 |
Safety |
Yes |
|
Violation Items
Citation ID |
01001 |
Citaton Type |
Serious |
Standard Cited |
19260850 C |
Issuance Date |
2022-10-25 |
Abatement Due Date |
2022-11-18 |
Current Penalty |
4351.0 |
Initial Penalty |
4351.0 |
Final Order |
2022-11-21 |
Nr Instances |
1 |
Nr Exposed |
3 |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.850(c): All electric, gas, water, steam, sewer, and other service lines were not shut off, capped, and/or otherwise controlled, outside the building line before demolition work was started: (a) At the worksite: On or about 10/3/2022, the general contractor for the jobsite, did not have the electrical power turned off or disconnected while the demolition work and expansion of the existing building was being performed, exposing workers to electrical shock hazards. |
|
|